The electrical connection of a new home incurs costs that can vary significantly depending on the geographical area, the requested power, and the distance to the network. Understanding these discrepancies requires distinguishing between the connection itself (Enedis work) and the commissioning of the meter, two items that many homeowners confuse when budgeting their project.
Enedis Connection Rates by Area and Power
The prices for individual connections are set by Enedis according to a regulated scale, updated periodically. They depend on the service area (ZFA or ZFB) and the chosen connection power. The table below lists the amounts as of July 1, 2026, for a power of 36 kVA or less.
You may also like : Everything You Need to Know About the World of IT: News, Tips, and Innovations
| Area | Connection Power | Price Excl. Tax | Price Incl. Tax (20% VAT) |
|---|---|---|---|
| ZFA | 3 kVA without metering | 1,629 € | 1,954.80 € Incl. Tax |
| ZFA | 12 kVA single-phase | 1,716 € | 2,059.20 € |
| ZFA | 36 kVA three-phase | 1,796 € | 2,155.20 € |
| ZFB | 3 kVA without metering | 1,810 € | 2,172 € |
| ZFB | 12 kVA single-phase | 1,830 € | 2,196 € |
These rates cover a standard connection up to 30 meters between the public network and the property boundary. Beyond 30 meters, an additional charge per linear meter applies, which can significantly increase the bill for isolated plots or those at the back of a property.
To better anticipate the cost of EDF and Enedis connection, it is essential to factor in the distance between the planned connection box and the existing network from the outset, as this is the primary factor causing discrepancies between two quotes.
Related reading : Everything You Need to Know About the Organization and Structure of a Shoe Enthusiast Website

Connection and Commissioning: Two Items Not to Confuse
A common confusion is to combine connection and commissioning into a single “EDF connection” budget. These are two distinct services, billed separately, with different contacts.
The connection refers to the physical work carried out by Enedis to connect your electrical installation to the distribution network. It concerns new homes or buildings that have never been connected. The quote is prepared by Enedis after a technical study that assesses the appropriate connection solution.
The commissioning, on the other hand, occurs once the connection is completed and the Consuel certificate is obtained. It involves activating the meter so that electricity flows. For a Linky meter, this operation is done remotely, in less than 24 hours, for a fee of 1.78 € Incl. Tax. This amount contrasts with the thousands of euros for the connection, but the two items appear on different invoices.
What the Enedis Quote Includes and Excludes
The connection quote covers the connection between the public network and the delivery point (box at the property boundary or facade). However, the work between the box and the interior electrical panel remains the responsibility of the owner. This part, carried out by an electrician, represents an additional item that varies according to the length of the trench on the property and the complexity of the interior installation.
- The Enedis connection covers the public network up to the delivery point, including the supply and installation of the meter.
- The interior electrical installation (from the box to the panel) is the responsibility of an independent electrician, billed separately.
- The Consuel certificate, mandatory before any commissioning, incurs its own cost related to the compliance certificate.
- The commissioning of the meter is ordered from an electricity supplier (EDF, Engie, etc.), not directly from Enedis.
Actual Timelines for a New Electrical Connection
The timelines announced by Enedis for a simple connection range from one to four months. This figure reflects only part of the actual project schedule.
The complete sequence begins with the connection request (online on the Enedis portal or by registered mail). Enedis then conducts a technical study to determine the connection solution, and then issues a proposal. The total timeline can extend over several months when the project requires an extension of the existing network, roadworks, or municipal permits.
After the connection work, the Consuel certificate must still be obtained before requesting commissioning. This compliance step, often underestimated, can add several weeks if the interior installation has non-compliance issues to correct.
Anticipating Timelines in the Construction Schedule
For a new home, the common recommendation is to submit the connection request at least four months before the planned move-in date. This timeline takes into account the technical study, Enedis work, the electrician’s intervention, and the Consuel inspection.
An undeveloped plot extends this timeline, as the network must first be extended to the parcel. In this case, the Enedis quote includes the extension costs, which depend on the distance and nature of the terrain to be crossed.

Distance to the Network: The Factor That Affects the Bill
The standard scale covers a connection up to 30 meters. Beyond that, each additional meter is charged extra, according to a unit price that depends on the type of terrain (public road, private path, agricultural land).
For a plot located in a serviced subdivision, the connection generally remains within the lower range of the scale. The connection box is already at the property boundary, and the distance to cover is limited to a few meters.
In contrast, an isolated plot in a rural area may require several dozen meters of trenching, or even a network extension. The price difference between a serviced plot and an undeveloped plot can easily reach several thousand euros. This is a parameter to check before purchasing the land, by requesting a preliminary estimate on the Enedis portal.
The choice between single-phase and three-phase also influences the price, but to a lesser extent. A 36 kVA three-phase connection in ZFA costs about 100 € Excl. Tax more than a 12 kVA single-phase. The power should be chosen based on the planned equipment (heat pump, charging station, professional use), not just the connection price.
The electrical connection remains a predictable budget item as long as the right information is gathered in advance: service area, distance to the network, necessary power. The Enedis quote, free and without obligation, provides the exact amount before any commitment to work.